Turnkey Electrical Project — 500-Bed Hospital Expansion, Hyderabad

🏥 Hospitals & Healthcare📍 Hyderabad, Telangana
38 days
Full project delivered (vs. 42-day target)
1 vendor
Complete accountability, no gaps
< 10 sec
Critical power changeover time
CEIG clearance — first attempt
Products & ServicesTurnkey ProjectDistribution TransformerLT PanelsVCB PanelDiesel GeneratorATS Panel
Overview

A 500-bed hospital in Hyderabad was adding a new surgical and ICU block. The project required a complete electrical installation — from HT incomer to critical circuit distribution — to be commissioned before the block opening, with a hard 6-week deadline.

The Challenge

Hospital electrical infrastructure is among the most demanding in the industry — it must meet NABH standards, pass CEIG inspection, provide sub-second critical power transfer, and deliver zero-downtime operation from day one. Coordinating multiple vendors (transformer, panels, DG, cables, earthing) within a 6-week construction window, with no room for schedule slip, required a single-vendor approach.

The Actaan Solution

Actaan Electric executed the project on a complete turnkey basis: SLD design and load scheduling, supply of a 500 kVA distribution transformer, 11kV VCB incomer panel, LT MDB with critical/essential/normal circuit segregation, 250 kVA DG set with AMF panel for sub-10-second changeover, HT/LT cable laying and termination, earthing system, and CEIG inspection coordination. The block was energised and handed over on day 38.

Scope of Supply & Work

  • ·Electrical SLD design and CEIG-compliant documentation
  • ·500 kVA distribution transformer (Actaan manufactured)
  • ·11kV VCB incomer panel with numerical relay protection
  • ·LT MDB with critical / essential / normal circuit segregation
  • ·250 kVA DG set with sub-10-second AMF changeover panel
  • ·HT and LT cable laying, glanding, and termination
  • ·Earthing and lightning protection system
  • ·CEIG inspection coordination and clearance

Results

38 days
Full project delivered (vs. 42-day target)
1 vendor
Complete accountability, no gaps
< 10 sec
Critical power changeover time
CEIG clearance — first attempt
More Case Studies

Other projects by Actaan Electric.

Get Started

Have a similar requirement?

Share your specification — kVA rating, voltage, application, location. We will review and respond with a technical proposal.

Send Your Requirement →